From rising tariffs to pandemic-era shipping chaos and environmental shutdowns in China, our customers were facing increasing pressure to secure their supply of critical castings—particularly high-volume counterweights. They needed a trusted partner with boots on the ground, deep engineering know-how, and the capability to qualify and manage new suppliers quickly. EQI stepped in with a proven plan.
Well before global headlines made diversification urgent, EQI began investing in an India-based supply chain strategy. Since 2014, we’ve developed and qualified multiple Indian foundries capable of delivering large, high-specification counterweights. For our two anchor customers, we led a phased transition that started with their highest-volume SKUs.
For our two anchor customers, we led a phased transition that started with their highest-volume SKUs. EQI handled:
Even during the most turbulent supply chain periods, we helped them shift 25–30% of their tonnage to India—giving them the flexibility to maintain production when others couldn’t.
As of 2025, these customers are now sourcing 60–70% of their counterweight needs from India, and that number continues to rise. Our infrastructure supports rapid expansion thanks to:
With Indian operations already integrated, our customers are ready to mitigate the next wave of tariffs without delay.
EQI-owned Berea, KY counterweight coating and distribution facility
EQI-owned Williamsport, MD counterweight coating and distribution facility
We’ve built the roadmap—and we’re ready to lead you through it. EQI’s India-based supply chain services are backed by our engineering, procurement, and logistics teams in both the U.S. and India. That means faster transitions, better visibility, and consistent quality. Most importantly, we have the capacity to scale and support future movements to India.
Here’s how fast your shift to India can happen:
Engineering review & supplier quotes
2–4 weeks
Tooling & sample production
4–5 weeks
1–2 weeks
Sample approval & shipping
Up to 8 weeks (faster with remote/onsite approvals)
Initial ocean freight transit
7–8 weeks
Engineering review & supplier quotes2–4 weeks
Tooling & sample production4–5 weeks
Engineering review & supplier quotes1–2 weeks
Sample approval & shippingUp to 8 weeks (faster with remote/onsite approvals)
Initial ocean freight transit7–8 weeks
Whether you need a full-scale transition or a risk-mitigation dual source, EQI has the capacity, experience, and supplier network ready to go. Interested in learning more about building resilient supply chains? Let’s talk.